Lease and work letter review
Confirm the tenant improvement allowance, delivery condition of the shell, landlord approval process, and who carries base-building upgrades. Every downstream budget decision depends on this document.
A working guide for developers, owners, and business operators planning a high-end office, retail, or hospitality buildout in South Florida — written from the field experience Group 72 has built delivering commercial and luxury residential work in Miami.
In Miami, a luxury commercial buildout converts a shell or an outdated space into a finished environment for an office, showroom, restaurant, clinic, or flagship retail brand. The visible work is millwork, stone, lighting, and glazing. The work that determines whether a tenant opens on time is permitting, base-building coordination, and procurement.
Two projects with identical drawings can differ by months depending on how early the lease work letter was read, how honestly existing conditions were surveyed, and how quickly long-lead materials were released. Those three decisions happen before construction starts.
"The finish is what people see. The sequence is what they feel."
Confirm the tenant improvement allowance, delivery condition of the shell, landlord approval process, and who carries base-building upgrades. Every downstream budget decision depends on this document.
Field-verify slab-to-slab heights, structural penetrations, MEP capacity, and any concealed conditions. In older Miami stock this is where schedule risk hides.
Price against coordinated drawings, not concepts. Line-item the finish package separately so ownership can trade material grade without reopening the whole budget.
Map the master permit and MEP subpermits, association review, Certificate of Use, and any DERM or health review. Sequence submittals so demolition and rough-in are not waiting on finish-level approvals.
Release stone, millwork, specialty lighting, glazing, and custom hardware first. On luxury commercial work these items — not labor — set the completion date.
Coordinate hoisting windows, protection of common areas, after-hours work rules, and noise restrictions with building management before mobilization.
Build mockups for critical details — reveal lines, stone joints, integrated lighting. Approving a detail on site is faster and cheaper than correcting it across an entire floor.
Inspections, commissioning, punch, warranties, as-builts, and owner training. A disciplined closeout is what allows a tenant to open on the date they announced.
Any change to the exterior envelope — storefront, glazing, louvers — is governed by Florida's high-velocity hurricane zone requirements, which affect both product selection and lead times.
Stone, veneer, and fine joinery must be acclimated and detailed for humidity. Metal specifications near the water need corrosion-resistant grades and finishes.
Buildouts inside oceanfront and downtown towers run on restricted hoisting windows, protected common areas, and association-approved work hours. Logistics belong in the schedule, not the punch list.
Preconstruction review of your lease, drawings, and site conditions is where a commercial buildout budget is won or lost. Tell us about the space and we'll tell you what it will really take.